Sum hours against project

Home Forums SPJS Charts for SharePoint Sum hours against project

Viewing 4 reply threads
  • Author
    Posts
    • #32004
      Phil Grant
      Participant

        Hi,
        It’s been a while since I ‘ve worked with charts so I may be asking a silly question but I’m trying to get a column chart to show a total of hours against different projects.

        I have Index 0 set to project (String and Index 1 set to Actual Hrs (number), group by first column and Aggregation set to Sum. but I can’t get a valid chart.

        If I set Aggegration to count It shows the total number of entries but not when I set it to Sum.

        Any suggestions?

        Cheers,
        Phil

      • #32026
        Alexander Bautz
        Keymaster

          Do you get an error message or just an empty chart? Is the Actual Hrs a number field or a single line of text field?

          Also, which version of SPJS Charts are you running?

          Alexander

        • #32028
          Phil Grant
          Participant

            The chart is not empty but looks strange (image attached).
            The version is v6.1.5.13.
            The field is a number.

            Strangley if I use the ID field it does sum the values of the ID, could it be because the number has 2 decimal places?

            Attachments:
          • #32031
            Phil Grant
            Participant

              Found the problem, there are two fields with numbers in and the one I picked doesn’t actually have any values in so that’s why it wouldn’t work, I picked the wrong field from the sample records we added.

              Sorry to waste your time.

            • #32033
              Alexander Bautz
              Keymaster

                No problem, I’m glad you figured it out.

                Alexander

            Viewing 4 reply threads
            • You must be logged in to reply to this topic.